Graceton to Manor Circuit Rebuild to Single Structure Line

Project Timeline

1.4 Miles

Project Timeline

230kV

Project Overview

The Graceton to Manor Reliability Upgrade project focuses on the partial rebuild of the existing electrical transmission line that runs from the Graceton Substation to the Pennsylvania/Maryland state line in Northern Harford County. This project consists of the demolition of eight steel tower structures and construction of nine new steel poles. A single circuit will be installed initially, leaving space for future expansion.

As part of this upgrade, a new three-wire transmission line will be installed on the west side of the newly installed poles, along with dual overhead fiber optic cables (OPGW). Construction for this project is scheduled to begin in late 2025.

Construction Activity

Construction Activities

Work on the Graceton to Manor project is scheduled to occur from January 2026 through the first half of June 2026. Project crews will pause work from June until September 2026. Construction will restart in September 2026 and continue construction through the end of the year.   

 

Month January – June June – August September – December
Construction Activity Ongoing Paused Ongoing

 

 

Project Timeline

Project Timeline

*Timeline is subject to change pending engineering and regulatory review.

Contact BGE

If you have any questions about these projects, please contact BGE at tri-county@goodenergyinprogress.com and refer to the BGE Graceton to Manor project. Please include your name and address for prompt follow-up.

tri-county@goodenergyinprogress.com





    This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.