Project Overview

The Lieb Road Transmission Upgrade Project involves rebuilding a section of the existing 230kV transmission line in northern Baltimore County and installing an additional 500kV transmission line to maintain the stability of the transmission grid. This project will span 1.5 miles starting at the Maryland-Pennsylvania line, heading south, entirely located on existing BGE right-of-way. PJM has directed BGE to complete this project by June 2027.

Permitting

One of the permits required for the Lieb Road Project is called a Certificate of Public Convenience and Necessity (CPCN). BGE has recently submitted its CPCN application with the Maryland Public Service Commission (PSC), a state agency that regulates public utilities like BGE, which the PSC has docketed as Case No. 9882. BGE’s CPCN application includes extensive information related to the Project and is available to you electronically on the PSC’s website at: https://webpscxb.pscmaryland.com/DMS/case/9882.

Hard copies of the CPCN application will also be available for reviewing at the following public libraries:

  • Baltimore County Public Library Hereford Branch,16940 York Road, Hereford, Maryland 21111
  • Harford County Public Library Norrisville Branch, 5310 Norrisville Road, White Hall, Maryland 21161

The PSC provides opportunities for public comments in the CPCN process, as well as the opportunity to seek to intervene as party in the CPCN proceeding. The PSC has sent Friday, July 17, 2026, as the deadline for persons to file petitions to intervene in this case.

More information about the procedural schedule and important dates for public comment and intervention for the Lieb Road Project can be found by visiting the Case No. 9882 docket on the PSC’s website at: https://webpscxb.pscmaryland.com/DMS/case/9882. You may reach out to the PSC directly for further information about the CPCN process using the contact information provided on their website.

Prior to construction, you may begin to see some additional foot traffic and activity on the existing BGE right-of-way related to surveying and other activities. If you have any questions or concerns, please contact the project team using the contact information below. The next meeting will be held virtually at 6:00pm on Wednesday, July 22, 2026. To register for this meeting please visit https://BGELiebRd1.eventbrite.com.

Project Timeline

Project Timeline

*Timeline is subject to change pending engineering and regulatory review.

Contact BGE

If you have any questions about these projects, please contact BGE at tri-county@goodenergyinprogress.com and refer to the BGE Lieb Road project. Please include your name and address for prompt follow-up.