29.1 Miles
230kV
This project involves the construction of a new 29.1-mile double-circuit transmission line in existing BGE right-of-way. The line will start at the existing 230kV Graceton Substation in Harford County and head south, tap off at the existing Bagley Substation, head further south passing in the vicinity of the Raphael Rd and Northeast Substations, and then terminate at the new Batavia Road Substation in Baltimore County.
*Timeline is subject to change pending engineering and regulatory review.
If you have any questions about these projects, please contact BGE at brandonshores@goodenergyinprogress.com and refer to the BGE Brandon Shores Retirement Mitigation. Please include your name and address for prompt follow-up.